Portland General Electric

An 11,000 SQ/FT tenant improvement for PGE at World Trade Center. The design called for a combination of ceiling systems, including ACT, open-to-structure, 9Wood, and hard lid assemblies, all blending seamlessly to create a modern, high-end environment. Despite procurement challenges due to material lead times, our proactive approach to scheduling and communication maintained project momentum.

We leveraged strategic sequencing, early material coordination, and daily collaboration between the field and design teams to overcome these obstacles. By adjusting our workflow and staying flexible, we successfully delivered the project on schedule without compromising quality or safety.

Client

PGE

Square Footage

11000

Project Cost

$1M – $1.5M

Completed in

15 weeks

Budgeted

15 weeks

Year of Completion

2025